Kitchen Renovation Cost in Malaysia 2026: Cabinets per Foot Run, Worktops and Two Worked Examples

Published 19 October 2026 · 9 min read · By the Wakkiro team
A renovated L-shaped condo kitchen in Malaysia with white melamine cabinets, a solid-surface worktop, a slim cooker hood and an induction hob

A kitchen renovation in Malaysia runs from about RM8,000 for a refresh to RM60,000 or more for a premium wet + dry kitchen. In our two worked examples below, a 10 ft L-shape condo kitchen with new melamine cabinets, a solid-surface worktop, new floor tiles and new appliances comes to about RM17,500–RM18,000. A terrace house split into a dry and a wet kitchen comes to about RM37,600–RM38,700.

This guide shows where that money goes: cabinets per foot run, worktop choices, hacking, plumbing and gas, electrical points for the hob, oven and hood, tiling and ceiling. Builder's work is priced from Wakkiro's material, labour and productivity rates (Selangor). Cabinets, worktops and appliances are not in our rate sheet, so those figures are labelled market ranges.

Kitchen renovation cost by tier

These tiers match the ranges in our Malay-language guide to kitchen renovation costs, so you can compare the two.

TierTypical scopeBudget
RefreshNew wall and floor tiles, paint, new sink and tap, existing cabinets kept or re-facedRM8,000 – RM15,000
Standard rebuildFull base and wall cabinets, new worktop, extra wiring, new hood and hobRM18,000 – RM35,000
Wet + dry kitchenKitchen split into a display dry kitchen and a working wet kitchen, sometimes with a small rear extensionRM30,000 – RM50,000
PremiumIsland, quartz or granite tops, spray-painted cabinets, concealed lightingRM40,000 – RM60,000+

The worked examples below show that cabinets, worktops and appliances make up most of a kitchen budget. In the condo example they are 78% of the total. Builder's work such as hacking, tiles, plumbing and wiring is the smaller part, but it is the part that is hardest to redo later.

Cabinet cost per foot run

Cabinet makers in Malaysia quote per foot run, meaning per foot of cabinet length along the wall. Base cabinets and wall cabinets are usually counted separately. These are market ranges per foot run for supply and installation, the same as in our Malay guide:

Cabinet materialPer foot runBest for
Melamine on particleboard or plywood carcassRM250 – RM400Dry kitchens and condo kitchens. Ask for a plywood carcass near the sink
AluminiumRM350 – RM550Wet kitchens. Unaffected by water and termites
Solid wood (e.g. nyatoh) with spray finishRM500 – RM800Durable and can be refinished, but heavy
Spray-painted MDFRM600 – RM900Smoothest modern finish. Keep away from wet zones

Two things change the price within each range: the carcass board (plywood is more moisture-resistant than particleboard) and the hardware (soft-close hinges and drawer runners). Ask for both in writing.

Worktops: quartz vs granite vs solid surface

Our rate sheet has no worktop prices, so the figures below are market assumptions per foot run used in our examples, not quotes:

Worktop thickness (12 mm vs 20 mm) and the number of cut-outs for the sink and hob also affect the price. The worktop is templated only after the base cabinets are installed, so allow 3–7 extra days.

Builder's work: hacking, plumbing, gas, wiring, tiles, ceiling

Hacking and disposal. Removing old cabinets and floor tiles is labour at RM120 a day in our sheet. A 10-wheel lorry with tipping fees is RM350 a trip for a landed house. In a condo, debris has to be bagged and taken down the service lift, so we use a RM400 market assumption, plus RM180 for four sheets of 9 mm plywood to protect the lift.

Plumbing. A plumber and helper cost RM260 a day. Keeping the sink where it is costs the least. Moving it two metres means hacking the floor and laying a new waste pipe with enough fall, which our Malay guide estimates adds RM1,500–RM3,000.

Gas. Most landed homes use an LPG cylinder with a regulator and hose. Where a condo has piped gas, any change to the gas pipework must be done by a registered gas contractor, not the general contractor. Check this before you move the hob.

Electrical points. An induction hob or built-in oven needs its own 20–30A circuit. The hood usually runs from a 13A socket above the cabinet. Market prices per point, from our guide to wiring point prices, are RM220–RM350 for a 30A point, RM90–RM140 for a 13A socket and RM80–RM120 for a lighting point. Put every point in before tiling starts.

Tiles. A tiler and assistant cost RM250 a day: 12 m² of floor a day (RM20.83 per m²) and 8 m² of wall a day (RM31.25 per m²). Homogeneous 600x600 floor tiles are RM41.67 per m² and ceramic 300x600 wall tiles RM22.22 per m² in our sheet. A 50 mm screed, where needed, is about RM33 per m² installed.

Ceiling. A 6 mm cement-board ceiling on a metal frame is about RM48 per m² installed. A wet kitchen ceiling takes a lot of steam and oil, so a washable finish is worth having.

Worked example 1: 10 ft L-shape condo kitchen

Assumptions: an L-shaped kitchen with legs of 10 ft and 6 ft (16 ft of base cabinets), 12 ft of wall cabinets, and a 10 x 7 ft floor (6.50 m²). The sink stays in place. Old floor tiles are replaced with homogeneous 600x600, and a 600 mm-high ceramic backsplash runs along 16 ft (2.93 m²). The existing ceiling is kept.

ItemWorkingCost (RM)
Strip-out and hacking3 labour-days × RM120360
Debris removal and lift protectionRM400 (market) + 4 plywood sheets × RM45580
Floor screed6.50 m² × RM33.41217
Floor tiles 600x600Materials RM315 + labour 6.50 m² × RM20.83450
Backsplash tiles 300x600Materials RM79 + labour 2.93 m² × RM31.25170
Plumbing1 day × RM260 + RM200 fittings (market)460
Electrical points30A hob RM285 + hood socket RM115 + 3 sockets × RM115 + 1 light RM100845
Painting15 m² × RM5.9289
Builder's work, direct3,172
Builder's overhead and profit 15%–30%3,172 × 1.15 to × 1.303,647 – 4,123
Base cabinets, melamine16 ft × RM325 (market midpoint)5,200
Wall cabinets, melamine12 ft × RM3253,900
Solid-surface worktop16 ft × RM120 (market assumption)1,920
Hood, hob, sink and tapMarket assumption, mid-range2,800
Total17,467 – 17,943

We add margin only to the builder's work. Cabinet and appliance prices from suppliers already include their margin. At about RM17,500–RM18,000 this kitchen sits just under the standard tier, because a condo kitchen is small and the ceiling and walls are kept.

Terrace house wet kitchen with full-height tiles, aluminium cabinets, granite worktop, gas hob and a glass sliding partition to the dry kitchen
Terrace house wet kitchen with full-height tiles, aluminium cabinets, granite worktop, gas hob and a glass sliding partition to the dry kitchen

Worked example 2: terrace house wet + dry kitchen

Assumptions: the existing rear kitchen of a terrace house is split into a 10 x 10 ft dry kitchen and an 8 x 10 ft wet kitchen, with a glass sliding partition between them. No extension. The wet kitchen gets full-height wall tiles (18.59 m² after the back door) and a new ceiling. The dry kitchen gets a 12 ft backsplash. Both floors (16.72 m²) are re-tiled.

ItemWorkingCost (RM)
Hacking and disposal2 labourers × 3 days × RM120 + 1 lorry trip RM3501,070
Floor screed16.72 m² × RM33.41559
Floor tiles 600x600Materials RM810 + labour RM3481,158
Wall tiles (wet kitchen full height + dry backsplash)20.78 m²: materials RM559 + labour RM6501,209
Plumbing (two sinks, floor trap)2 days × RM260 + RM400 fittings (market)920
Electrical points2 × 30A RM570 + 8 sockets × RM115 + 3 lights × RM1001,790
Wet kitchen ceiling7.43 m² × RM48.46360
Painting dry kitchen25 m² × RM5.92148
Builder's work, direct7,214
Builder's overhead and profit 15%–30%7,214 × 1.15 to × 1.308,296 – 9,378
Dry kitchen cabinets, melamine12 ft base + 12 ft wall × RM3257,800
Dry kitchen quartz worktop12 ft × RM300 (market assumption)3,600
Wet kitchen cabinets, aluminium10 ft base + 8 ft wall × RM4508,100
Wet kitchen granite worktop10 ft × RM220 (market assumption)2,200
Two hoods, two hobs, two sinks2 × RM2,800 (market)5,600
Glass sliding partitionMarket assumption2,000
Total37,596 – 38,678

This lands in the middle of the wet + dry tier. If your wet kitchen needs to be built as a new rear extension rather than carved out of the existing kitchen, the structure, roof and permit come on top. See our guides to extension costs in Malaysia and the Malay kos tambah bilik extension.

Condo vs landed: what changes

What a kitchen quote should include

Usually included:

Usually not included unless stated:

How to check a kitchen renovation quote

  1. Divide cabinets by foot run. Check the base and wall cabinet lengths against your own tape measure, then divide the cabinet price by the length. Compare the result with the ranges above for the material quoted.
  2. Look for the electrical schedule. A list such as "1 × 30A hob, 1 × 20A oven, 1 × 13A hood, 4 × 13A sockets" means the contractor has planned the circuits. "Wiring as required" is a warning sign.
  3. Check the order of works. Hacking, plumbing and wiring first, then tiles, then cabinets, then the worktop template. A contractor who delivers cabinets before the tiles are done will end up doing work twice.
  4. Ask who does the electrical and gas work. Electrical work must be done by a wireman registered with Suruhanjaya Tenaga. Piped gas changes need a registered gas contractor.
  5. Stage the payments. A deposit against cabinet fabrication is normal. Pay the balance after installation and the snag list.

To compare line by line, see how to read a BOQ. If the kitchen is part of a bigger renovation, upload your plan to Wakkiro for an itemised BOQ before you collect quotes.

What would your project actually cost?

Upload a drawing or describe the job — Wakkiro builds an itemised BOQ at current Malaysian rates, free.

Estimate My Project →

Frequently Asked Questions

How much does a kitchen renovation cost in Malaysia in 2026?

Roughly RM8,000–RM15,000 for a refresh, RM18,000–RM35,000 for a standard rebuild with new cabinets and worktop, RM30,000–RM50,000 for a wet + dry kitchen and RM40,000–RM60,000+ for a premium kitchen. Our 10 ft L-shape condo example comes to about RM17,500–RM18,000.

What is the cost of kitchen cabinets per foot run in Malaysia?

Market ranges for supply and installation are RM250–RM400 per foot run for melamine, RM350–RM550 for aluminium, RM500–RM800 for solid wood and RM600–RM900 for spray-painted MDF. Base and wall cabinets are usually counted separately.

Quartz, granite or solid surface: which worktop is cheapest?

In our market assumptions, solid surface is about RM120 per foot run, granite about RM220 and quartz about RM300. Granite handles heat best for wok cooking, quartz resists scratches and stains, and solid surface is easiest to repair.

How much does a wet and dry kitchen cost?

Our example of a terrace kitchen split into a 10 x 10 ft dry kitchen and an 8 x 10 ft wet kitchen, with a glass partition, comes to about RM37,600–RM38,700. That includes melamine and aluminium cabinets, quartz and granite tops, two sets of appliances and full-height wet kitchen tiles. A new rear extension costs extra.

What electrical points does a kitchen need?

An induction hob or built-in oven needs its own 20–30A circuit, at about RM220–RM350 per point. The hood and small appliances use 13A sockets at RM90–RM140 each. Install all points before tiling, using a wireman registered with Suruhanjaya Tenaga.

Get a full itemised estimate, free

Line-by-line BOQ for a new build, extension or renovation — in minutes.

Start Now →
About this guide. Written by the Wakkiro team using the material, labour and productivity rates in the Wakkiro price database (Selangor, Kuala Lumpur, Johor), checked against a practising site engineer's pricing. Published 19 October 2026. Seen different prices in your area? Tell us.