Construction Cost Malaysia 2027: Forecast Cost per sq ft by Building Type, State and Scenario

Published 28 November 2026 · 10 min read · By Dr. Daing Hanum · Price data: Rasydan Abdulah, site engineer

Baca panduan ini dalam Bahasa Malaysia →

Double-storey terrace houses under construction in a Malaysian housing estate, with scaffolding, a ready-mix truck and a tower of red bricks

Wakkiro estimate for 2027: building a house in Malaysia should cost about RM186–RM238 per sq ft for basic spec, RM259–RM341 for standard and RM362–RM466 for premium. That is about 3.4% above our 2026 benchmark. Our low and high scenarios are +1.3% and +6.2%. Renovation rises a little faster, about 3.8%, because it is more labour-heavy.

This handbook-style guide gives 2027 psf ranges by building type and state, the inputs behind the forecast (DOSM's October 2026 building cost index, wage data and the Budget 2027 minimum wage), a worked example on a RM264,000 house, and what to do about timing, price locks and contingency.

Building cost per sq ft Malaysia 2027: the forecast table

These are our estimates for a complete house on your own land, contractor's profit included, land and consultants excluded. The 2026 column is our published benchmark from the guide to the cost to build a house in Malaysia. The 2027 columns apply the cost model explained further down.

Specification2026 (RM psf)2027 low (+1.3%)2027 base (+3.4%)2027 high (+6.2%)
Basic: simple finishes, metal deck roofRM180–RM230RM182–RM233RM186–RM238RM191–RM244
Standard: porcelain tiles, concrete roof tilesRM250–RM330RM253–RM334RM259–RM341RM265–RM350
Premium: imported finishes, high ceilingsRM350–RM450+RM355–RM456RM362–RM466RM372–RM478

In RM per m², the standard base band is RM2,788–RM3,671 (psf × 10.764). The spread between low and high is only about 5 points. What moves you most within a year is still specification and soil, not the calendar.

2026 vs 2027 cost by building type

Renovation and extension work carry more labour, so they rise slightly faster than new builds in our model (+3.8% and +3.5% base). The two real projects below were priced by our site engineer in 2026; the 2027 figures are those prices × 1.0345, rounded to the nearest RM1,000.

Building type20262027 base
Single-storey house, standard spec, 1,075 sq ft (real project)RM295,000 (RM274 psf)about RM305,000 (RM284 psf)
Double-storey premium bungalow, Johor, 4,262 sq ft (real project)RM1,100,000 (RM258 psf gross, RM427 per enclosed sq ft)about RM1,138,000
Renovation, light refresh (terrace)RM20,000–RM50,000RM20,800–RM51,900
Renovation, mid scopeRM60,000–RM120,000RM62,300–RM124,500
Renovation, majorRM120,000–RM250,000RM124,500–RM259,400
Ground-floor rear extension (A&A)RM150–RM220 psfRM155–RM228 psf
Side or front extensionRM130–RM200 psfRM135–RM207 psf
Upper-floor extensionRM220–RM320 psfRM228–RM331 psf

Terrace and semi-D new builds: we have no engineer-priced terrace or semi-D in our project set, so we do not publish a separate band. Use the spec bands above. An intermediate terrace usually lands in the lower half of its band because it shares both side walls. On a 40 × 50 ft two-storey footprint, a bungalow has about 54.9 m of external wall against roughly 13.4 m for an intermediate terrace. Render and weatherproof paint alone cost about RM42 per m² in our rates. A semi-D sits between the two. Bungalows have their own pitfalls, covered in our guide to the cost to build a bungalow in Malaysia.

Construction cost in KL, Selangor and Johor for 2027

DOSM's material index is rising faster in Johor (+3.3% y/y in October 2026) than in the Selangor/KL/Melaka/Negeri Sembilan region (+1.7%). So we apply each region's own trend instead of one national figure. That gives +3.0% for KL and Selangor and +3.9% for Johor (base case).

StateBasic 2027Standard 2027Premium 2027
Kuala LumpurRM196–RM252RM273–RM361RM386–RM494
SelangorRM185–RM237RM258–RM340RM361–RM464
JohorRM177–RM229RM249–RM327RM348–RM447

Johor still comes out cheaper than Selangor, but the gap narrows. For the other states, start from the 2026 table in house building cost by state and add about 3.4%.

How we built the 2027 forecast

We did not take a consultant's headline number and apply it to houses. We split our 2026 cost into three parts, then applied a sourced change to each part.

ScenarioMaterials (55%)Labour (37%)Other (8%)Total change
Low+0.5% → 0.275+2.5% → 0.925+1.8% → 0.144+1.34%
Base+2.5% → 1.375+5.0% → 1.850+2.8% → 0.224+3.45%
High+5.0% → 2.750+8.0% → 2.960+6.0% → 0.480+6.19%

For renovation we use 42% materials, 50% labour and 8% other, because hacking and making-good are slow. That gives +1.6% / +3.8% / +6.6%. Extensions (51/41/8) come out at +1.4% / +3.5% / +6.3%.

Worked example: the RM264,000 house in 2027

Our 2026 reference is a 1,000 sq ft single-storey house, standard spec, in Selangor: RM264,000 including prelims and statutory contributions. Split it first: materials 264,000 × 55% = RM145,200; labour × 37% = RM97,680; other × 8% = RM21,120. Those three add back to RM264,000.

ScenarioMaterialsLabourOtherIncrease2027 total
Low145,200 × 0.5% = RM726.0097,680 × 2.5% = RM2,442.0021,120 × 1.8% = RM380.16RM3,548.16RM267,548
Base145,200 × 2.5% = RM3,630.0097,680 × 5.0% = RM4,884.0021,120 × 2.8% = RM591.36RM9,105.36RM273,105
High145,200 × 5.0% = RM7,260.0097,680 × 8.0% = RM7,814.4021,120 × 6.0% = RM1,267.20RM16,341.60RM280,342

So the same house costs about RM9,100 more in our base case, a range of RM3,500 to RM16,300. Labour contributes more of the increase than materials, even though materials are the bigger share.

Ready-mix concrete being poured over BRC mesh for a house ground slab, the material whose price rose most in 2026
Ready-mix concrete being poured over BRC mesh for a house ground slab, the material whose price rose most in 2026

Market outlook: what published sources say

Why the gap between 3% and 15%? The higher claims cover the whole of a contractor's cost since February, including diesel, lorries, plant and infrastructure work. DOSM's house index tracks building materials only. Unsubsidised diesel has also fallen, from RM5.52 a litre at the end of March to RM4.47 for 26 November–2 December 2026.

Tender price index Malaysia 2027

CIDB publishes a tender price index, and quantity surveying consultants publish their own tender price forecasts and cost handbooks. We could not verify a 2027 figure for Malaysia from any of them, so we do not quote one. Our +3.4% base is a cost forecast built bottom-up for houses. It is not a tender price index. Tender prices can move differently, because contractors with full order books add margin. That is a real risk in 2027, as data centre and rail jobs compete for MEP trades and ready-mix.

Cost drivers to watch in 2027

The other Budget 2027 measures for home buyers and builders are covered in what Budget 2027 means for house costs.

What a psf figure includes, and what it leaves out

How to check a contractor's quote in 2027

What this means for you

All 2027 figures are Wakkiro estimates, not quotations. We will update them when DOSM publishes the December 2026 index.

What would your project actually cost?

Upload a drawing or describe the job — Wakkiro builds an itemised BOQ at current Malaysian rates, free.

Estimate My Project →

Frequently Asked Questions

How much will it cost to build a house in Malaysia in 2027?

Our base estimate is RM186–RM238 per sq ft for basic spec, RM259–RM341 for standard and RM362–RM466 for premium, before land and consultant fees. That is about 3.4% above 2026. A 1,000 sq ft standard single-storey house in Selangor goes from RM264,000 to about RM273,105.

Will construction costs in Malaysia go up or down in 2027?

Up, but moderately. DOSM's house material index rose 1.6–3.3% in the year to October 2026, steel is falling and diesel has eased from its March peak. Wages are rising about 5% a year, and the minimum wage rises to RM2,000 in June 2027. Our range is +1.3% to +6.2%, with +3.4% as the base case.

What is the construction cost per sq ft in KL, Selangor and Johor in 2027?

For standard spec, our 2027 base estimate is RM273–RM361 psf in Kuala Lumpur, RM258–RM340 in Selangor and RM249–RM327 in Johor. Johor's material costs are rising faster (+3.3% vs +1.7% y/y), so its gap with Selangor narrows.

Does the RM2,000 minimum wage make building a house more expensive?

Slightly. It takes effect in June 2027, so it lifts affected wages by about 10.3% averaged over 2027. Firms with sales below RM50 million are exempt, and most small builders' day rates are already above RM2,000 a month. In our high case it adds about 3 points to labour cost, or around 1.1% to a new house.

How much contingency should I keep for a 2027 build or renovation?

At least 10% for a new build and 12–15% for renovating an older house. If works run into late 2027 without a fixed price, add about 3% as an escalation allowance, the gap between our base and high scenarios.

Get a full itemised estimate, free

Line-by-line BOQ for a new build, extension or renovation — in minutes.

Start Now →
About this guide. Written and reviewed by Dr. Daing Hanum, with price data from our site engineer Rasydan Abdulah. Figures come from the Wakkiro rate book and the sources named in the article. Drafts are prepared with AI writing assistance and checked before publishing; see our editorial policy. Seeing a different price in your area? Tell us.