Quantity Takeoff in Malaysia 2026: How Each Trade Is Measured, With a Worked Room Takeoff

Published 28 November 2026 · 9 min read · By Dr. Daing Hanum · Price data: Rasydan Abdulah, site engineer
Quantity surveyor's desk with a printed house floor plan, scale ruler, calculator and a handwritten measurement sheet

A quantity takeoff is the measured list of everything a job needs: m² of brickwork, plaster, paint and tiles, m³ of concrete, kg of steel bar, metres of skirting and the number of doors and points. Malaysian quantity surveyors measure it net, from the drawings, under the SMM2 rules. Done properly for one 3.6 m × 3.0 m bedroom, walls plus finishes come to about RM5,800 in direct cost, or RM6,700–RM7,500 once a contractor adds 15%–30% overhead and profit (Selangor/KL/Johor rates).

This article goes through how each trade is measured: units, deduction rules, where wastage goes and the usual mistakes. Then it works through a full takeoff of that room, line by line, priced from the Wakkiro rate book. It also covers taking off from a floor plan or a hand sketch, and how to check the quantities in a contractor's quote.

What is a quantity takeoff?

A takeoff answers "how much?" before anyone asks "how much does it cost?". The QS reads the plans, sections and elevations and turns every element into a measured quantity with a unit. Only after that is each quantity multiplied by a unit rate.

The takeoff is the raw measurement. The bill of quantities (BOQ) is the finished document: those quantities grouped into trades, given standard descriptions and priced. If you already have a BOQ and want to understand its columns and sections, our guide on how to read a BOQ covers that. This page is about how the numbers in the quantity column are produced.

The measurement rules Malaysian QS use (SMM2)

Most Malaysian BOQs are measured to the Standard Method of Measurement of Building Works, Second Edition (SMM2), published in 2000 by the Institution of Surveyors Malaysia (now RISM). Every QS measures to the same rules, so two bills for the same drawing should give the same quantities. These rules matter most on a house:

The abbreviations you will see beside these quantities (m², m³, nr, L/S, PC, PS) are listed in our BOQ abbreviations guide.

How each trade is measured: units and conventions

TradeUnitHow it is measuredWastage / extras (in the rate, not the quantity)
Excavationm³Trench or pit size as dug, from the foundation planBulking of loose soil and disposal trips
Hardcore under slabm² (stated thickness)Slab area, e.g. 150 mm crusher runAbout 0.28 tonne per m² compacted, plus 5%
Concretem³Length × width × depth of each slab, beam, column, footing3%–5% spillage, plus pump hire on upper floors
Formworkm²Area of formwork touching the concrete (soffits and sides)Plywood reuse, cutting, about 10%
Steel barkg or tonneBar length from the bending schedule × unit weight (T12 = 0.888 kg/m)Offcuts, tying wire, about 5%
BRC meshm²Net slab area300 mm laps, about 0.088 sheet per m²
Brick / block wallm²Centreline length × height, less openings5% bricks; mortar in the rate
Plaster, skim coatm²Each face plastered, less voids over 0.50 m²10% plaster droppings, 5% skim coat
Floor screed and tilesm²Room area, wall to wall5% tiles (7.5% in rooms under 10 m²)
Wall tilesm²Tiled face, less openings7.5% (many cuts in bathrooms)
Skirting, cornicem runRoom perimeter, less door widths for skirtingMitres and offcuts
Ceiling boardm²Room area7.5% board cutting
Roof coveringm²Area on the slope, not on plan (plan area ÷ cos of pitch: ×1.155 at 30°)Side and end laps, about 10% on metal sheet
Ridge, hip, flashingm runMeasured lengthLaps
Doors, windows, sanitary, pointsnrCounted from the plan and the door/window scheduleNone

The most common homeowner mistake is measuring the roof on plan. A 1,200 sq ft roof plan with a 30° pitch is about 1,386 sq ft of tiles on the slope, roughly 15% more material than a plan measurement shows.

Worked takeoff: one 3.6 m × 3.0 m bedroom

The room is 3.6 m × 3.0 m inside, with 3.0 m floor-to-ceiling height, half-brick (115 mm) clay brick walls, one 0.9 × 2.1 m door and one 1.2 × 1.2 m window. Foundations, slab, roof, doors, windows and wiring are left out so the measuring stays easy to follow. Rates are direct cost (materials plus labour) from the Wakkiro rate book.

Step 1: measure the quantities

Step 2: price the quantities

ItemQtyUnitRate (RM)Amount (RM)
115 mm clay brick wall in cement mortar 1:337.65m²67.682,548.15
12 mm cement-sand plaster 1:4 to walls36.27m²24.29881.00
Skim coat, base + finishing coat36.27m²12.93468.97
Emulsion paint to walls, sealer + 2 coats36.27m²5.92214.72
Emulsion paint to ceiling, sealer + 2 coats10.80m²5.9263.94
50 mm cement-sand floor screed10.80m²33.41360.83
600 × 600 mm homogeneous floor tiles on adhesive10.80m²68.01734.51
6 mm fibre-cement board ceiling on frame10.80m²48.46523.37
Direct cost5,795.49
With 15% overhead and profit6,664.81
With 30% overhead and profit7,534.14

Divide RM5,795.49 by 116.25 sq ft and you get about RM50 psf, and that's before structure, roof, doors, windows or wiring. A single psf figure hides a lot, and a takeoff shows you what sits inside it.

How a unit rate is built

Each rate is quantity of material per m² × material price, plus crew day rate ÷ output per day. For the brick wall:

The floor tile rate works the same way: 2.78 tiles per m² × 1.05 × RM15 = RM43.79, adhesive 0.22 bag × RM13.80 = RM3.04, grout cement RM0.36, and tiler plus assistant RM250 ÷ 12 m² per day = RM20.83, giving RM68.01 per m². Laying rates by tile size are compared in our tile laying price guide.

From measured quantity to order quantity

The BOQ carries the net quantity. The site order adds wastage and rounds up to whole bags, boxes and boards. Keeping the two separate stops wastage being counted twice, once in the quantity and again in the rate.

MaterialNet calculationOrder
Clay bricks37.65 m² × 62 × 1.05 = 2,451 pcs2,500 pcs
Cement for brickwork and plaster37.65 × 0.2 = 7.53 bags + 36.27 × 0.11 × 1.10 = 4.39 bags12 bags
Cement for screed10.80 × 0.48 × 1.075 = 5.57 bags6 bags
600 × 600 floor tiles10.80 × 2.78 = 30.02 pcs, × 1.05 = 31.5332 pcs (8 boxes of 4)
Ceiling boards 1220 × 244010.80 × 0.34 × 1.075 = 3.954 boards
Measuring a plastered wall and door opening on site to check the takeoff quantities
Measuring a plastered wall and door opening on site to check the takeoff quantities

Takeoff from a floor plan or hand sketch

A measured takeoff needs only a few things. A sketch with these is enough for a budget BOQ:

For built-up area (BUA), our site engineer uses one convention throughout. Measure to the outside face of the building and to the edge of the car porch columns. Roofed space counts in full even if it has no walls. Roof overhang, coping and unroofed driveways are not BUA; they are external works. Getting this wrong moves a psf budget by thousands of ringgit, and our guide to estimating from architectural drawings shows where these areas appear on a plan set.

On a renovation, the engineer measures and prices each part as its own block. In one renovation-and-extension job, the split was extension RM108,686, alterations RM6,500 lump sum and roof RM18,300. Each block has its own quantities, so you can see where the money goes. If you want this done from your own drawing, you can upload a plan or a clear photo of a dimensioned sketch to Wakkiro and get an itemised BOQ.

What a takeoff-based quote includes, and what it often leaves out

How to check the quantities in a contractor's quote

What would your project actually cost?

Upload a drawing or describe the job — Wakkiro builds an itemised BOQ at current Malaysian rates, free.

Estimate My Project →

Frequently Asked Questions

What is quantity takeoff in construction?

It is the measurement of every element of a job from the drawings: m² of walls and finishes, m³ of concrete, kg of steel bar, metres of skirting and the number of doors and points. The quantities are then priced at unit rates to form the bill of quantities (BOQ).

What is the difference between a takeoff and a BOQ?

The takeoff is the raw measurement. The BOQ is the finished document that groups those quantities into trades, gives each one a standard description and prices it. A good BOQ shows the quantity column, so the takeoff can be checked.

Which measurement standard do quantity surveyors use in Malaysia?

Most use SMM2, the Standard Method of Measurement of Building Works, Second Edition, published in 2000 by the Institution of Surveyors Malaysia (now RISM). It measures work net as fixed, to the nearest 10 mm, with set rules for deducting openings.

Do you deduct doors and windows when measuring walls?

Yes, when they are large enough. Under SMM2, brickwork ignores voids up to 0.10 m², and plaster and paint ignore voids up to 0.50 m². A normal door (about 1.89 m²) or window (about 1.44 m²) is always deducted.

Is wastage included in the quantities?

Not in a properly measured BOQ. Quantities are net and wastage goes into the rate, for example 5% for bricks and floor tiles and 7.5% for wall tiles. Your order quantity adds the wastage and rounds up to whole bags or boxes.

Can I get a takeoff from a hand-drawn sketch?

Yes, if it shows room dimensions or a scale, ceiling height, door and window sizes and wall types. Check the scale against one printed dimension first. A sketch is good enough for a budget BOQ, but not for a tender.

Get a full itemised estimate, free

Line-by-line BOQ for a new build, extension or renovation — in minutes.

Start Now →
About this guide. Written and reviewed by Dr. Daing Hanum, with price data from our site engineer Rasydan Abdulah. Figures come from the Wakkiro rate book and the sources named in the article. Drafts are prepared with AI writing assistance and checked before publishing; see our editorial policy. Seeing a different price in your area? Tell us.