Quantity Takeoff in Malaysia 2026: How Each Trade Is Measured, With a Worked Room Takeoff
A quantity takeoff is the measured list of everything a job needs: m² of brickwork, plaster, paint and tiles, m³ of concrete, kg of steel bar, metres of skirting and the number of doors and points. Malaysian quantity surveyors measure it net, from the drawings, under the SMM2 rules. Done properly for one 3.6 m × 3.0 m bedroom, walls plus finishes come to about RM5,800 in direct cost, or RM6,700–RM7,500 once a contractor adds 15%–30% overhead and profit (Selangor/KL/Johor rates).
This article goes through how each trade is measured: units, deduction rules, where wastage goes and the usual mistakes. Then it works through a full takeoff of that room, line by line, priced from the Wakkiro rate book. It also covers taking off from a floor plan or a hand sketch, and how to check the quantities in a contractor's quote.
What is a quantity takeoff?
A takeoff answers "how much?" before anyone asks "how much does it cost?". The QS reads the plans, sections and elevations and turns every element into a measured quantity with a unit. Only after that is each quantity multiplied by a unit rate.
The takeoff is the raw measurement. The bill of quantities (BOQ) is the finished document: those quantities grouped into trades, given standard descriptions and priced. If you already have a BOQ and want to understand its columns and sections, our guide on how to read a BOQ covers that. This page is about how the numbers in the quantity column are produced.
The measurement rules Malaysian QS use (SMM2)
Most Malaysian BOQs are measured to the Standard Method of Measurement of Building Works, Second Edition (SMM2), published in 2000 by the Institution of Surveyors Malaysia (now RISM). Every QS measures to the same rules, so two bills for the same drawing should give the same quantities. These rules matter most on a house:
- Measure net, as fixed in position. The quantity is the finished work, not what gets delivered to site. Wastage, laps and cutting go into the rate.
- Dimensions to the nearest 10 mm. 5 mm and over rounds up and anything under 5 mm is ignored.
- Brick and block walls in m², taken on the centreline for the wall area. Voids up to 0.10 m² are not deducted, but an opening on the edge of the wall is always deducted.
- Plaster, render, paint and coverings in m² on the face that gets the finish. Voids up to 0.50 m² are not deducted, so a 0.3 m² vent is ignored while a 1.89 m² door is deducted.
- Linear items in metres run: skirting, cornice, ridge, gutters, pipes, kerbs.
- Countable items by number (nr): doors, windows, sanitary fittings, light and power points.
The abbreviations you will see beside these quantities (m², m³, nr, L/S, PC, PS) are listed in our BOQ abbreviations guide.
How each trade is measured: units and conventions
| Trade | Unit | How it is measured | Wastage / extras (in the rate, not the quantity) |
|---|---|---|---|
| Excavation | m³ | Trench or pit size as dug, from the foundation plan | Bulking of loose soil and disposal trips |
| Hardcore under slab | m² (stated thickness) | Slab area, e.g. 150 mm crusher run | About 0.28 tonne per m² compacted, plus 5% |
| Concrete | m³ | Length × width × depth of each slab, beam, column, footing | 3%–5% spillage, plus pump hire on upper floors |
| Formwork | m² | Area of formwork touching the concrete (soffits and sides) | Plywood reuse, cutting, about 10% |
| Steel bar | kg or tonne | Bar length from the bending schedule × unit weight (T12 = 0.888 kg/m) | Offcuts, tying wire, about 5% |
| BRC mesh | m² | Net slab area | 300 mm laps, about 0.088 sheet per m² |
| Brick / block wall | m² | Centreline length × height, less openings | 5% bricks; mortar in the rate |
| Plaster, skim coat | m² | Each face plastered, less voids over 0.50 m² | 10% plaster droppings, 5% skim coat |
| Floor screed and tiles | m² | Room area, wall to wall | 5% tiles (7.5% in rooms under 10 m²) |
| Wall tiles | m² | Tiled face, less openings | 7.5% (many cuts in bathrooms) |
| Skirting, cornice | m run | Room perimeter, less door widths for skirting | Mitres and offcuts |
| Ceiling board | m² | Room area | 7.5% board cutting |
| Roof covering | m² | Area on the slope, not on plan (plan area ÷ cos of pitch: ×1.155 at 30°) | Side and end laps, about 10% on metal sheet |
| Ridge, hip, flashing | m run | Measured length | Laps |
| Doors, windows, sanitary, points | nr | Counted from the plan and the door/window schedule | None |
The most common homeowner mistake is measuring the roof on plan. A 1,200 sq ft roof plan with a 30° pitch is about 1,386 sq ft of tiles on the slope, roughly 15% more material than a plan measurement shows.
Worked takeoff: one 3.6 m × 3.0 m bedroom
The room is 3.6 m × 3.0 m inside, with 3.0 m floor-to-ceiling height, half-brick (115 mm) clay brick walls, one 0.9 × 2.1 m door and one 1.2 × 1.2 m window. Foundations, slab, roof, doors, windows and wiring are left out so the measuring stays easy to follow. Rates are direct cost (materials plus labour) from the Wakkiro rate book.
Step 1: measure the quantities
- Openings: door 0.9 × 2.1 = 1.89 m²; window 1.2 × 1.2 = 1.44 m²; total 3.33 m². Both are over 0.50 m², so they are deducted from every trade.
- Brickwork (centreline): internal girth 2 × (3.6 + 3.0) = 13.20 m, plus 4 corners × 0.115 m = 0.46 m, giving 13.66 m. Gross 13.66 × 3.0 = 40.98 m², less 3.33 = 37.65 m².
- Plaster, skim coat, paint (inside face only): 13.20 × 3.0 = 39.60 m², less 3.33 = 36.27 m². The outer faces are measured with the next room or as external render.
- Floor screed, floor tiles, ceiling, ceiling paint: 3.6 × 3.0 = 10.80 m² (116.25 sq ft).
- Skirting (measured, priced separately): 13.20 − 0.90 door = 12.30 m run.
Step 2: price the quantities
| Item | Qty | Unit | Rate (RM) | Amount (RM) |
|---|---|---|---|---|
| 115 mm clay brick wall in cement mortar 1:3 | 37.65 | m² | 67.68 | 2,548.15 |
| 12 mm cement-sand plaster 1:4 to walls | 36.27 | m² | 24.29 | 881.00 |
| Skim coat, base + finishing coat | 36.27 | m² | 12.93 | 468.97 |
| Emulsion paint to walls, sealer + 2 coats | 36.27 | m² | 5.92 | 214.72 |
| Emulsion paint to ceiling, sealer + 2 coats | 10.80 | m² | 5.92 | 63.94 |
| 50 mm cement-sand floor screed | 10.80 | m² | 33.41 | 360.83 |
| 600 × 600 mm homogeneous floor tiles on adhesive | 10.80 | m² | 68.01 | 734.51 |
| 6 mm fibre-cement board ceiling on frame | 10.80 | m² | 48.46 | 523.37 |
| Direct cost | 5,795.49 | |||
| With 15% overhead and profit | 6,664.81 | |||
| With 30% overhead and profit | 7,534.14 | |||
Divide RM5,795.49 by 116.25 sq ft and you get about RM50 psf, and that's before structure, roof, doors, windows or wiring. A single psf figure hides a lot, and a takeoff shows you what sits inside it.
How a unit rate is built
Each rate is quantity of material per m² × material price, plus crew day rate ÷ output per day. For the brick wall:
- Bricks: 62 per m² × 1.05 wastage × RM0.53 = RM34.50
- Cement: 0.2 bag × RM26 = RM5.20
- Sand: 0.0033 load × RM902 = RM2.98
- Labour: bricklayer RM130 + assistant RM95 = RM225 per day ÷ 9 m² per day = RM25.00
- Total: RM67.68 per m²
The floor tile rate works the same way: 2.78 tiles per m² × 1.05 × RM15 = RM43.79, adhesive 0.22 bag × RM13.80 = RM3.04, grout cement RM0.36, and tiler plus assistant RM250 ÷ 12 m² per day = RM20.83, giving RM68.01 per m². Laying rates by tile size are compared in our tile laying price guide.
From measured quantity to order quantity
The BOQ carries the net quantity. The site order adds wastage and rounds up to whole bags, boxes and boards. Keeping the two separate stops wastage being counted twice, once in the quantity and again in the rate.
| Material | Net calculation | Order |
|---|---|---|
| Clay bricks | 37.65 m² × 62 × 1.05 = 2,451 pcs | 2,500 pcs |
| Cement for brickwork and plaster | 37.65 × 0.2 = 7.53 bags + 36.27 × 0.11 × 1.10 = 4.39 bags | 12 bags |
| Cement for screed | 10.80 × 0.48 × 1.075 = 5.57 bags | 6 bags |
| 600 × 600 floor tiles | 10.80 × 2.78 = 30.02 pcs, × 1.05 = 31.53 | 32 pcs (8 boxes of 4) |
| Ceiling boards 1220 × 2440 | 10.80 × 0.34 × 1.075 = 3.95 | 4 boards |

Takeoff from a floor plan or hand sketch
A measured takeoff needs only a few things. A sketch with these is enough for a budget BOQ:
- Overall dimensions and room dimensions in mm or feet, or a scale bar. Check the scale against one printed dimension before measuring anything else, because a photocopied A3 plan is often no longer to scale.
- Floor-to-ceiling height, usually 3.0 m on new houses; old terraces vary.
- Door and window sizes, from a schedule or marked on the plan (D1, W1).
- Wall type: brick, block or existing to remain.
- Roof form and pitch, from an elevation or section.
For built-up area (BUA), our site engineer uses one convention throughout. Measure to the outside face of the building and to the edge of the car porch columns. Roofed space counts in full even if it has no walls. Roof overhang, coping and unroofed driveways are not BUA; they are external works. Getting this wrong moves a psf budget by thousands of ringgit, and our guide to estimating from architectural drawings shows where these areas appear on a plan set.
On a renovation, the engineer measures and prices each part as its own block. In one renovation-and-extension job, the split was extension RM108,686, alterations RM6,500 lump sum and roof RM18,300. Each block has its own quantities, so you can see where the money goes. If you want this done from your own drawing, you can upload a plan or a clear photo of a dimensioned sketch to Wakkiro and get an itemised BOQ.
What a takeoff-based quote includes, and what it often leaves out
- Usually included: measured quantities for each trade, the rate for each line, materials with normal wastage, labour, and small tools.
- Often priced separately: preliminaries (scaffolding, debris disposal at about RM350 per lorry trip, site water and power), plant hire, and overhead and profit.
- Often left out or shown as provisional sums: piling, soil investigation, M&E, kitchen cabinets, sanitary fittings, PBT plan approval and professional fees.
- Not measured at all: anything that isn't on the drawing. Ask for those to be written in as provisional sums so they don't come back later as variations.
How to check the quantities in a contractor's quote
- Pick two easy lines and re-measure them. Floor area and wall paint area are quick to check. If the floor tiles show 14 m² for a 10.8 m² room, ask why.
- Look for wastage counted twice. A quantity of "11.88 m²" for a 10.80 m² floor already has 10% added. Either the quantity or the rate should carry wastage, not both.
- Check the units. 1 m² = 10.764 sq ft. A rate in RM per sq ft against a quantity in m² overstates that line about 10.8 times.
- Watch for large lump sums (L/S) on measurable work such as tiling or plastering. Measurable work should be measured.
- Compare against your plan's BUA using the convention above, and against our cost to build a house in Malaysia ranges for the house type.
Upload a drawing or describe the job — Wakkiro builds an itemised BOQ at current Malaysian rates, free.
Estimate My Project →Frequently Asked Questions
What is quantity takeoff in construction?
It is the measurement of every element of a job from the drawings: m² of walls and finishes, m³ of concrete, kg of steel bar, metres of skirting and the number of doors and points. The quantities are then priced at unit rates to form the bill of quantities (BOQ).
What is the difference between a takeoff and a BOQ?
The takeoff is the raw measurement. The BOQ is the finished document that groups those quantities into trades, gives each one a standard description and prices it. A good BOQ shows the quantity column, so the takeoff can be checked.
Which measurement standard do quantity surveyors use in Malaysia?
Most use SMM2, the Standard Method of Measurement of Building Works, Second Edition, published in 2000 by the Institution of Surveyors Malaysia (now RISM). It measures work net as fixed, to the nearest 10 mm, with set rules for deducting openings.
Do you deduct doors and windows when measuring walls?
Yes, when they are large enough. Under SMM2, brickwork ignores voids up to 0.10 m², and plaster and paint ignore voids up to 0.50 m². A normal door (about 1.89 m²) or window (about 1.44 m²) is always deducted.
Is wastage included in the quantities?
Not in a properly measured BOQ. Quantities are net and wastage goes into the rate, for example 5% for bricks and floor tiles and 7.5% for wall tiles. Your order quantity adds the wastage and rounds up to whole bags or boxes.
Can I get a takeoff from a hand-drawn sketch?
Yes, if it shows room dimensions or a scale, ceiling height, door and window sizes and wall types. Check the scale against one printed dimension first. A sketch is good enough for a budget BOQ, but not for a tender.